1.
Call to
Order at
2.
Welcome and
General announcements – Jim Carpenter
Purpose of Meeting: To review the current engineering plans for Jefferson
Streetscape.
The web site for the Jefferson Streetscape project is found at
http://JeffersonMd.net/Streetscape.
3.
The following
people attended:
Jim Carpenter, Maurice Hoffmaster, Marshall Wisner, Joe Horman, Gene Keller,
Mike Boyer, Andy Lynn, Shirley Hale, David Phillips (SHA), David Coyne (SHA),
Brick Remsburg, Tom Arnold, Mike Summers
4.
Minutes of last
meeting.
The last Streetscape meeting was held
5.
Review of SHA
engineering plans – lead by David Phillips
David Phillips noted that engineering specifications for the previous plans
called for replacement of the existing curb to improve drainage and facilitate
the reconstruction of existing sidewalks. With previous years of overlaying with
no grinding of the pavement there is now little or no reveal on the existing
face of the curbs in some areas. David Coyne noted that SHA now grinds and
resurfaces a roadway rather then overlay it. Due to this little or no reveal, if
SHA were to replace the curbs in those areas adjacent buildings may be impacted.
These impacts would be a result of the sidewalk having to be raised 6 to 8
inches with the new curb and the resulting grading to keep positive drainage
away from houses.
The first option SHA explored to alleviate these impacts was to lower the
roadway. This would result in the complete reconstruction of Jefferson Pike and
would cost about $15 million for the 1900 feet between
After considerable calculations, SHA finally developed a plan that would satisfy
drainage and other objectives for an acceptable cost, currently estimated to be
$2.5 million. This current plan
calls for installing a 6 to 8 inch high curb. Behind this curb, at roadway
level, would be a slotted grate drain and then a concrete sidewalk.
This would allow the sidewalk and landscape between houses and the curb
to slope downwards toward the drain without impacting adjacent structures.
Each lane of traffic would be at least 11 feet (from center line to
curb). This design would eliminate
most of the parking shown in the previous concept.
The sidewalks would be 5 feet wide, according to Americans with
Disabilities Act (ADA) requirements or would have to receive a waiver if less
then 5 feet wide.
David Phillips pointed out two issues of possible concern to landowners.
(1) the area from the curb to the house (including drain and sidewalk)
belongs to the landowner who has the responsibility for maintenance.
(2) Almost all parking spaces will be lost between
David indicated that the “corridor” nature of the project (the curb must not be
interrupted except for driveways) means that 100% buy-in of property owners
would be required. All property
owners would need to sign a “Right of Entry” statement giving SHA temporary
rights to do the construction work.
Two property owners (Andy Lynn and Tom Arnold) indicated they had some
reservations about the plan but would have to study it further.
The committee viewed and discussed the drawing for the current and previous SHA
plans. The drawings will be stored
at the Jefferson Ruritan Center.
There was discussion of our three apparent options:
(1) Do nothing (cancel the Streetscape Project).
Periodic grinding and resurfacing would continue as in the past without
any improvement in sidewalks or drainage.
(2) Adopt the current plan at $2.5 million.
If 100% of owners approve, final engineering plans could be done and
ready for advertisement by next spring.
(3) Adopt previous plan at cost of over $18 million and hope for
approval, which is unlikely in a program that has a large number of projects
competing for a very limited amount of funding.
6.
Dave Coyne read
a letter from Board of County Commissioners that listed
7.
Next Steps.
The committee decided to request that SHA provide:
(1) a drawing of a typical cross section showing the new design with the
slotted grate drain, (2) a bulleted presentation to explain the new design and
why parking would have to be removed, (3) updated list of all property owners,
and (4) list of properties where there was on street parking in front of their
property in the previous plan but will be loosing that parking in the new plan.
David Phillips indicated that he would provide these items to Jim and
Andy by next week.
The committee decided to plan the next public meeting with property owners who
lose parking. The committee will
decide whether SHA presence will be needed at the meeting after reviewing the
above items from SHA.
8. Next Task Force Meeting. To be determined.
9.
Meeting
adjourned at